East Orange BOE Offices East Orange, NJ

<
>

East Orange Board of Education
The Vaughn Collaborative
GDS Mechanical, Inc.

Building Renovation
Construction Management Services
46,000 SF
$2,650,000
Complete

 

ShapiroCM was selected in April, 2012 to enter into a contract with the East Orange Board of Education, to provide Construction Management Services for renovation of an existing elementary school to house the new Board of Education District Offices.

The building renovation included interior demolition, new partitions, all MEP systems, New Fire sprinkler system, new elevators, Exterior repairs, window replacement and new interior finishes. ShapiroCM’s services included full-time on-site project/construction management services during construction and project close out.

Franklin School District Renovations Somerset, NJ

<
>

Franklin Township Board of Education
Faridy, Veitz, Fraytak
Various (Multi-Prime)

Renovations and Expansions (6 Schools)
Construction Management
48,000 SF
$6,300,000
Complete

ShapiroCM served as Construction Manager for renovations and expansions at 6 elementary and middle school facilities in this district. Construction activity took place both during summer recess as well as during the school term.

Scopes included new classrooms, multi-purpose spaces,and building systems upgrades. Contracts at each location comprised multi-prime awards, with CM coordination of all trades.

Neptune Aquatic Center Neptune, NJ

<
>

New Jersey SDA
Kellenyi, Wagner, Johnson
Patock Construction

New Swim Complex
CM Support Services
30,000 SF
$11,000,000
Complete

ShapiroCM provided CM Support Services to the Liro Group, managing construction of a new community pool complex at Neptune High School. The project was funded by the State of New Jersey SDA. Services included Project Schedule and Cost Control, as well as all Contract Documentation through successful completion.

New Franklin High School Franklin, NJ

<
>

Franklin Township Board of Education
Faridy Veisz, Fraytak
Multi-prime

New 2,000 Student High School
Construction Management (multi-prime)
340,000 SF
$63,000,000
Complete

ShapiroCM provided Construction Management services for the development of a new High School on a 100 Acre site in Somerset, NJ. ShapiroCM’s role included the management and coordination of a “multi-prime” contracting structure- for school opening in the fall of 2005. Services include all aspects of project and construction management including phasing and staging, cost control, schedule control, quality control, and field oversight on this major project, one of the largest new high schools in New Jersey, at the time.

Roberto Clemente Kindergarten Center Paterson, NJ

<
>

New Jersey SDA
Charles Maillet
Delric Construction

Conversion of Industrial Building to K-School
Construction Management Services
8,000 SF
$2,300,000
Complete

As prime CM to NJSDA, ShapiroCM managed the conversion of an existing commercial building into four kindergarten classrooms, one multi-purpose room, a kitchen and administration spaces. The project included building a parking lot on a site remote to the main building site. The scope of work included a new roof and 5 HVAC roof top units. ShapiroCM successfully delivered this project to an on schedule completion in December 2009.